  1. Q1a. Which SDLC model explicitly incorporates risk analysis into every development cycle? (i) Waterfall (ii) Code-and-Fix (iii) Spiral (iv) Incremental20262m

    Module 1: Introduction & SDLC

    Which SDLC model explicitly incorporates risk analysis into every development cycle?

    (i) Waterfall
    (ii) Code-and-Fix
    (iii) Spiral
    (iv) Incremental

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (iii) Spiral

    Explanation

    The Spiral Model (Barry Boehm) is a risk-driven process model. Every loop of the spiral contains an explicit Risk Analysis phase, where risks are identified and resolved (often through prototyping) before the next loop begins.

    Why other options are incorrect:

    • (i) Waterfall - Linear and sequential; has no explicit risk analysis step.
    • (ii) Code-and-Fix - Ad hoc coding with no planning or risk handling.
    • (iv) Incremental - Delivers the product in increments, but does not build risk analysis into every cycle.

    Key Points to Remember:

    • Four quadrants of Spiral: Objective Setting, Risk Assessment & Reduction, Development & Validation, Planning.
    • Best suited for large, complex, high-risk projects.

    Answer: (iii) Spiral

  2. Q1b. Brooks' "No Silver Bullet" argument primarily concerns the difficulty of reducing (i) Hardware cost (ii) Compilation time (iii) Essential complexity of software (iv) Database size20262m

    Module 1: Introduction & SDLC

    Brooks' "No Silver Bullet" argument primarily concerns the difficulty of reducing

    (i) Hardware cost
    (ii) Compilation time
    (iii) Essential complexity of software
    (iv) Database size

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (iii) Essential complexity of software

    Explanation

    In his paper "No Silver Bullet" (1986), Fred Brooks separates software difficulty into:

    • Accidental complexity - caused by tools, languages and methods; technology can reduce it.
    • Essential complexity - inherent in the problem itself (complexity, conformity, changeability, invisibility).

    His argument: no single technique can give an order-of-magnitude improvement in productivity, because the hard part is the essential complexity of the problem, not the tools.

    Why other options are incorrect:

    • (i) Hardware cost and (iv) Database size - not part of Brooks' argument.
    • (ii) Compilation time - a tool-level (accidental) issue.

    Answer: (iii) Essential complexity of software

  3. Q1c. A requirement expected to change because of evolving business conditions is classified as (i) Enduring requirement (ii) Structural requirement (iii) Volatile requirement (iv) Derived requirement20262m

    Module 2: Requirements & SRS

    A requirement expected to change because of evolving business conditions is classified as

    (i) Enduring requirement
    (ii) Structural requirement
    (iii) Volatile requirement
    (iv) Derived requirement

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (iii) Volatile requirement

    Explanation

    Requirements are classified by how stable they are:

    • Enduring requirements - stable, tied to the core activity of the organization; they change rarely.
    • Volatile requirements - likely to change during development or after delivery because of evolving business conditions, policies, laws or technology.

    A requirement expected to change because of evolving business conditions is therefore volatile.

    Why other options are incorrect:

    • (i) Enduring - the opposite: stable and long-lasting.
    • (ii) Structural - not a standard stability category.
    • (iv) Derived - a requirement obtained from other requirements, not defined by how often it changes.

    Answer: (iii) Volatile requirement

  4. Q1d. Which characteristic of an SRS indicates that every requirement has only one clear interpretation? (i) Complete (ii) Unambiguous (iii) Consistent (iv) Modifiable20262m

    Module 2: Requirements & SRS

    Which characteristic of an SRS indicates that every requirement has only one clear interpretation?

    (i) Complete
    (ii) Unambiguous
    (iii) Consistent
    (iv) Modifiable

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (ii) Unambiguous

    Explanation

    An unambiguous SRS ensures that every requirement has exactly one interpretation, so the client, developers and testers all understand it the same way. This is achieved with precise language, defined terms, and formal or structured notations where needed.

    Why other options are incorrect:

    • (i) Complete - all required functions, constraints and interfaces are included.
    • (iii) Consistent - no requirement conflicts with another.
    • (iv) Modifiable - the document can be changed easily while keeping its structure.

    Key Points to Remember:

    Characteristics of a good SRS: correct, unambiguous, complete, consistent, ranked for importance, verifiable, modifiable, traceable.

    Answer: (ii) Unambiguous

  5. Q1e. Which combination generally represents desirable modular design? (i) High coupling and low cohesion (ii) Low coupling and high cohesion (iii) High coupling and high cohesion (iv) Low coupling and low cohesion20262m

    Module 3: Software Design & Metrics

    Which combination generally represents desirable modular design?

    (i) High coupling and low cohesion
    (ii) Low coupling and high cohesion
    (iii) High coupling and high cohesion
    (iv) Low coupling and low cohesion

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (ii) Low coupling and high cohesion

    Explanation

    • Cohesion = how strongly the elements inside one module are related. High is good.
    • Coupling = how dependent modules are on each other. Low is good.

    A good modular design has high cohesion within modules and low coupling between modules, which makes software easier to understand, test, maintain and reuse.

    Why other options are incorrect:

    • (i) High coupling, low cohesion - the worst combination.
    • (iii) High coupling, high cohesion - modules are focused but too dependent on each other.
    • (iv) Low coupling, low cohesion - independent modules, but each does unrelated things.

    Answer: (ii) Low coupling and high cohesion

  6. Q1f. A DFD primarily represents (i) Program execution time (ii) Source-code complexity (iii) Class inheritance (iv) Flow and transformation of data20262m

    Module 3: Software Design & Metrics

    A DFD primarily represents

    (i) Program execution time
    (ii) Source-code complexity
    (iii) Class inheritance
    (iv) Flow and transformation of data

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (iv) Flow and transformation of data

    Explanation

    A Data Flow Diagram (DFD) models how data flows through a system and how processes transform it. Its four elements are: processes, data flows, data stores and external entities.

    A DFD shows what happens to data, not when or how the code runs.

    Why other options are incorrect:

    • (i) Program execution time - not shown in a DFD.
    • (ii) Source-code complexity - measured by metrics such as cyclomatic complexity.
    • (iii) Class inheritance - shown in UML class diagrams.

    Answer: (iv) Flow and transformation of data

  7. Q1g. Which representation is most suitable for showing different actions corresponding to combinations of conditions? (i) Decision table (ii) Data dictionary (iii) Structure chart (iv) Control-flow graph20262m

    Module 2: Requirements & SRS

    Which representation is most suitable for showing different actions corresponding to combinations of conditions?

    (i) Decision table
    (ii) Data dictionary
    (iii) Structure chart
    (iv) Control-flow graph

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (i) Decision table

    Explanation

    A decision table lists conditions and the actions to take for each combination of those conditions, in a compact tabular form. Each column (rule) maps one combination of condition values to its actions, which makes it ideal for complex business logic.

    Why other options are incorrect:

    • (ii) Data dictionary - stores definitions of data items.
    • (iii) Structure chart - shows the module hierarchy and calls.
    • (iv) Control-flow graph - shows the flow of control in a program (used for path testing and cyclomatic complexity).

    Answer: (i) Decision table

  8. Q1h. Halstead's software science primarily uses counts of (i) Modules and classes (ii) Operators and operands (iii) Test cases and defects (iv) Inputs and outputs only20262m

    Module 3: Software Design & Metrics

    Halstead's software science primarily uses counts of

    (i) Modules and classes
    (ii) Operators and operands
    (iii) Test cases and defects
    (iv) Inputs and outputs only

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (ii) Operators and operands

    Explanation

    Halstead's software science measures a program using counts of its operators and operands:

    • n1 = distinct operators, n2 = distinct operands
    • N1 = total operators, N2 = total operands

    From these:

    • Vocabulary n = n1 + n2
    • Length N = N1 + N2
    • Volume V = N × log2(n)

    Why other options are incorrect:

    • (i) Modules and classes - used in design metrics, not Halstead.
    • (iii) Test cases and defects - testing/quality metrics.
    • (iv) Inputs and outputs only - that is closer to Function Point Analysis.

    Answer: (ii) Operators and operands

  9. Q1i. Cyclomatic complexity of a connected control-flow graph with E edges, N nodes and P connected components is (i) E+N+P (ii) E-N-P (iii) N-E+2P (iv) E-N+2P20262m

    Module 3: Software Design & Metrics

    Cyclomatic complexity of a connected control-flow graph with E edges, N nodes and P connected components is

    (i) E+N+P
    (ii) E-N-P
    (iii) N-E+2P
    (iv) E-N+2P

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (iv) E - N + 2P

    Explanation

    McCabe's cyclomatic complexity of a control-flow graph with E edges, N nodes and P connected components is:

    V(G) = E - N + 2P

    For a single connected program (P = 1) this becomes V(G) = E - N + 2. It also equals:

    • number of predicate (decision) nodes + 1
    • number of regions in the planar graph

    It gives the number of linearly independent paths, i.e. the minimum number of test cases for branch coverage.

    Why other options are incorrect:

    • (i) E+N+P, (ii) E-N-P, (iii) N-E+2P - not valid forms of the formula.

    Answer: (iv) E - N + 2P

  10. Q1j. Configuration management primarily provides control over (i) Software versions and changes (ii) Computer hardware temperature (iii) Programming language syntax (iv) Employee attendance20262m

    Module 5: Software Maintenance

    Configuration management primarily provides control over

    (i) Software versions and changes
    (ii) Computer hardware temperature
    (iii) Programming language syntax
    (iv) Employee attendance

    View this question on its own page →
    Worked Solution

    Solution

    Correct Answer: (i) Software versions and changes

    Explanation

    Software Configuration Management (SCM) controls how the items that make up a software product (code, documents, test cases, build scripts) change over time. Its main activities are:

    • Configuration identification - naming and versioning items
    • Version control - managing versions and branches
    • Change control - reviewing and approving changes
    • Configuration auditing and status reporting

    Why other options are incorrect:

    • (ii) Hardware temperature and (iv) Employee attendance - unrelated to SCM.
    • (iii) Language syntax - handled by compilers and coding standards.

    Answer: (i) Software versions and changes

  11. Budget App•POCKETLY

    Pocketly on Android

    Log daily food, travel, and hostel expenses instantly. Set monthly spending limits and see where your money goes without complex spreadsheets.

    Install Pocketly
  12. Q2a. A project manager is considering Waterfall, Incremental and Spiral models for a safety-critical system. Construct a comparative decision matrix using risk, requirement volatility, feedback and delivery characteristics and justify the selection criteria.20267m

    Module 1: Introduction & SDLC

    A project manager is considering Waterfall, Incremental and Spiral models for a safety-critical system. Construct a comparative decision matrix using risk, requirement volatility, feedback and delivery characteristics and justify the selection criteria.

    View this question on its own page →
    Worked Solution

    Decision Matrix: Waterfall vs Incremental vs Spiral for a Safety-Critical System

    Selection criteria

    For a safety-critical system a failure can cause injury or loss of life, so risk handling matters most. The other criteria are requirement volatility, feedback and delivery.

    Comparative matrix

    Criterion Waterfall Incremental Spiral
    Risk Weak: risks surface late, mostly during testing Moderate: risk handled per increment Strong: explicit risk analysis in every loop
    Requirement volatility Poor: requirements frozen early Good: new needs go into later increments Good: requirements refined every loop
    Feedback Late: only after testing/delivery After every increment After every loop (prototype + review)
    Delivery Single big-bang release Early partial working releases Versions/prototypes; final release after several loops

    Weighted score (scale 1 to 5, illustrative)

    Criterion (weight) Waterfall Incremental Spiral
    Risk (0.4) 2 3 5
    Volatility (0.2) 1 4 4
    Feedback (0.2) 1 4 4
    Delivery (0.2) 2 5 3
    Weighted total 1.6 3.8 4.2

    Example: Spiral = 0.4(5) + 0.2(4) + 0.2(4) + 0.2(3) = 4.2.

    Justification

    • Risk has the highest weight because hazards in a safety-critical system must be found and removed early.
    • Spiral scores highest: each loop has a risk-analysis step, prototypes are evaluated, and verification can be repeated before the next loop.
    • Waterfall gives strong documentation but finds risks too late and cannot absorb change.
    • Incremental gives early feedback but has no built-in risk analysis.

    Decision: Spiral, keeping Waterfall-style rigorous documentation, reviews and verification inside each loop. If the requirements are well understood and risk is low, Incremental is the fallback.

    Note: scores and weights are judgement-based; state your assumptions in the exam.

  13. Q2b. Compare Agile development with a conventional sequential process in terms of iteration, customer participation, requirement change and software delivery.20267m

    Module 1: Introduction & SDLC

    Compare Agile development with a conventional sequential process in terms of iteration, customer participation, requirement change and software delivery.

    View this question on its own page →
    Worked Solution

    Agile Development vs Conventional Sequential Process

    Sequential process (e.g. Waterfall): requirements, design, coding, testing and delivery happen once, in fixed order.
    Agile: software is built in short iterations (sprints) of 1 to 4 weeks, each producing a working increment, with continuous customer involvement.

    Comparison

    Aspect Agile Conventional sequential
    Iteration Many short iterations; every cycle repeats analysis, design, code and test Single pass through each phase; no return to earlier phases without rework
    Customer participation Continuous: customer reviews every iteration and prioritizes the backlog Mainly at the start (requirements) and end (acceptance)
    Requirement change Welcomed, even late; changes enter the backlog for later sprints Resisted; requirements frozen early, changes are costly
    Software delivery Frequent, working increments (every sprint) One delivery at the end of the project
    Documentation Light; working software valued over documents Heavy, formal, phase-wise
    Risk Found early through frequent feedback Found late, during testing
    Planning Adaptive; plan per iteration Detailed up-front plan
    Suitable for Changing or unclear requirements Stable, well-understood requirements

    Conclusion

    Agile gives faster feedback, easier handling of change and earlier value to the customer. A sequential process gives predictability and thorough documentation, which suits fixed, stable requirements. Examples of Agile methods: Scrum, XP, Kanban.

  14. Q3a. Construct an SRS-oriented requirement analysis for a hotel management system covering major user needs, functional requirements, constraints and quality requirements.20267m

    Module 2: Requirements & SRS

    Construct an SRS-oriented requirement analysis for a hotel management system covering major user needs, functional requirements, constraints and quality requirements.

    View this question on its own page →
    Worked Solution

    SRS-Oriented Requirement Analysis: Hotel Management System

    1. Introduction

    • Purpose: automate room booking, check-in/out, billing and housekeeping for a hotel.
    • Scope: reception, guests, housekeeping, restaurant billing, management reports.
    • Users: Guest, Receptionist, Housekeeping staff, Manager/Admin.

    2. Major user needs

    User Need
    Guest Search available rooms, book/cancel online, view bill
    Receptionist Quick check-in/out, room allocation, payment collection
    Housekeeping See room status (clean/dirty/occupied), task list
    Manager Occupancy, revenue and staff reports

    3. Functional requirements

    • FR1 Room management: add/update rooms, types and tariffs; show real-time availability.
    • FR2 Reservation: book, modify, cancel a room for given dates; prevent double booking.
    • FR3 Check-in/Check-out: record guest ID, allocate room, close the stay.
    • FR4 Billing: calculate room charges, taxes, restaurant/service charges; generate invoice.
    • FR5 Payment: cash, card and online payment; issue receipt.
    • FR6 Housekeeping: update and track room status.
    • FR7 Reports: daily occupancy, revenue, guest history.
    • FR8 User management: role-based login.

    4. Constraints

    • Must run on a web browser and a standard database (e.g. MySQL).
    • Must follow tax/billing laws and guest-ID record rules.
    • Payment through an approved gateway; fixed budget and delivery time.
    • Must work with existing hardware (reception PCs, printers).

    5. Quality (non-functional) requirements

    Quality Requirement
    Performance Search/booking response within 3 seconds for up to 100 concurrent users
    Security Encrypted passwords, role-based access, secure payments
    Reliability/Availability 99.5% uptime; daily backups
    Usability Simple screens; staff trained within one day
    Scalability Support more rooms/branches later
    Maintainability Modular design with documentation

    6. Assumptions

    Online payment gateway and internet are available; figures such as response time are assumed values.

    In the exam, present these in the IEEE SRS layout: Introduction, Overall Description, Specific Requirements.

  15. Q3b. Develop a decision table for an online loan-processing system using customer eligibility, income level, credit score and document verification as conditions. Derive the corresponding system actions.20267m

    Module 2: Requirements & SRS

    Develop a decision table for an online loan-processing system using customer eligibility, income level, credit score and document verification as conditions. Derive the corresponding system actions.

    View this question on its own page →
    Worked Solution

    Decision Table: Online Loan-Processing System

    Conditions

    • C1 Customer eligible? (Y/N)
    • C2 Income level adequate? (Y/N)
    • C3 Credit score good? (Y/N)
    • C4 Documents verified? (Y/N)

    Actions

    • A1 Approve loan
    • A2 Reject loan
    • A3 Request additional documents
    • A4 Refer to manual review (e.g. reduced amount or higher interest)

    Decision table ("-" = don't care)

    R1 R2 R3 R4 R5 R6
    C1 Eligible N Y Y Y Y Y
    C2 Income adequate - - Y Y N N
    C3 Credit score good - - Y N Y N
    C4 Documents verified - N Y Y Y Y
    A1 Approve loan X
    A2 Reject loan X X
    A3 Request documents X
    A4 Manual review X X

    Derived system actions

    1. R1: not eligible, so reject whatever the other conditions are.
    2. R2: eligible but documents not verified, so request more documents.
    3. R3: eligible, income adequate, good credit, documents verified, so approve.
    4. R4 / R5: eligible and documents verified, but only one of income/credit is satisfactory, so manual review.
    5. R6: eligible and documents verified, but both income and credit are poor, so reject.

    Completeness check

    Without "don't cares" the table needs 2^4 = 16 rules. R1 covers 8, R2 covers 4, and R3 to R6 cover 1 each (documents verified = Y), so 8 + 4 + 4 = 16: every combination is covered and none overlaps.

    The business rules above are assumptions; state them in the exam.

  16. Q4a. Compare different types of coupling and cohesion and determine which combination should be targeted for a maintainable modular system.20267m

    Module 3: Software Design & Metrics

    Compare different types of coupling and cohesion and determine which combination should be targeted for a maintainable modular system.

    View this question on its own page →
    Worked Solution

    Coupling and Cohesion: Types, Comparison and Target Combination

    Coupling = interdependence between modules (want it low).
    Cohesion = relatedness of elements within a module (want it high).

    Types of coupling (best to worst)

    Type Meaning Quality
    Data Modules share only simple parameters Best
    Stamp Share a composite structure (record) but use only part of it Good
    Control One module passes a flag that controls the other's logic Moderate
    External Share an external device, format or protocol Poor
    Common Share global data Poor
    Content One module modifies or jumps into another's internals Worst

    Types of cohesion (worst to best)

    Type Meaning Quality
    Coincidental Unrelated tasks grouped randomly Worst
    Logical Tasks of the same category, selected by a flag (e.g. all input routines) Poor
    Temporal Tasks executed at the same time (e.g. initialization) Poor
    Procedural Tasks follow a fixed order of execution Moderate
    Communicational Tasks work on the same data Good
    Sequential Output of one task is input to the next Better
    Functional All elements contribute to one single function Best

    Comparison

    Basis Coupling Cohesion
    Concerns Between modules Within a module
    Goal Minimize Maximize
    Measures Dependence Relatedness
    Effect when poor Changes ripple across modules Module is hard to understand

    Target combination for a maintainable modular system

    Low coupling (data coupling) with high cohesion (functional cohesion).

    • A change stays inside one module, so maintenance is cheaper.
    • Modules can be tested, reused and developed independently.
    • Errors do not spread to other modules.

    Avoid content/common coupling and coincidental/logical cohesion.

  17. Q4b. Construct a DFD for an online library system that supports registration, book search, issue/return and fine calculation. Show the major data stores and external entities.20267m

    Module 3: Software Design & Metrics

    Construct a DFD for an online library system that supports registration, book search, issue/return and fine calculation. Show the major data stores and external entities.

    View this question on its own page →
    Worked Solution

    DFD for an Online Library System

    Elements

    • External entities: Member, Librarian
    • Processes: 1.0 Register Member, 2.0 Search Book, 3.0 Issue Book, 4.0 Return Book, 5.0 Calculate Fine
    • Data stores: D1 Member File, D2 Book Catalogue, D3 Issue/Return Record, D4 Fine Record

    Level 0: Context diagram

                    registration details, search request,
                    issue / return request, fine payment
       [ Member ] ------------------------------------> (  0  Online  )
       [ Member ] <------------------------------------ (  Library    )
                    login status, search results,         (  System     )
                    issue slip, fine receipt                  ^   |
                                                              |   v
       [ Librarian ] -- book details, member approval --------+   |
       [ Librarian ] <-------- reports, overdue list -------------+
    

    Level 1 DFD

    [Member]--registration details-->(1.0 Register Member)--member record-->[D1 Member File]
    [Member]--search request-->(2.0 Search Book)<--book data--[D2 Book Catalogue]
    (2.0 Search Book)--search results-->[Member]
    [Member]--issue request-->(3.0 Issue Book)
    (3.0 Issue Book)<--member check--[D1 Member File]
    (3.0 Issue Book)<--availability / update copies-->[D2 Book Catalogue]
    (3.0 Issue Book)--issue entry-->[D3 Issue/Return Record]
    (3.0 Issue Book)--issue slip-->[Member]
    [Member]--return request-->(4.0 Return Book)
    (4.0 Return Book)<--issue entry-->[D3 Issue/Return Record]
    (4.0 Return Book)--update copies-->[D2 Book Catalogue]
    (4.0 Return Book)--return date-->(5.0 Calculate Fine)
    (5.0 Calculate Fine)--fine record-->[D4 Fine Record]
    (5.0 Calculate Fine)--fine receipt-->[Member]
    [Librarian]--book details-->[D2 Book Catalogue]
    [Librarian]<--overdue / fine reports--[D3, D4]
    

    Data flow summary

    Process Inputs Outputs
    1.0 Register Member Registration details Member record to D1, confirmation
    2.0 Search Book Search request, D2 data Search results
    3.0 Issue Book Issue request, D1, D2 Issue entry to D3, updated D2, issue slip
    4.0 Return Book Return request, D3 Updated D3 and D2, return date
    5.0 Calculate Fine Return date, due date Fine to D4, fine receipt

    Rules followed

    • Every process has at least one input and one output.
    • Data stores connect only to processes, never directly to entities.
    • Data flows are labelled; the Level 1 inputs and outputs match the context diagram (balancing).

    In the exam, draw the diagram with circles (processes), rectangles (entities), open rectangles (data stores) and labelled arrows.

  18. Q5a. For a program segment containing one loop and three conditional branches, construct its control-flow graph and calculate McCabe's cyclomatic complexity. Relate the result to the minimum number of independent paths.20267m

    Module 3: Software Design & Metrics

    For a program segment containing one loop and three conditional branches, construct its control-flow graph and calculate McCabe's cyclomatic complexity. Relate the result to the minimum number of independent paths.

    View this question on its own page →
    Worked Solution

    Control-Flow Graph and McCabe's Cyclomatic Complexity

    Assumed program segment (1 loop + 3 conditional branches)

    1  i = 0;
    2  while (i < n) {          // loop condition
    3     if (a[i] > 0)         // branch 1
    4         pos++;
    5     if (a[i] < 0)         // branch 2
    6         neg++;
    7     if (a[i] == 0)        // branch 3
    8         zero++;
    9     i++;
       }
    10 print(pos, neg, zero);
    

    Control-flow graph

    • Nodes (N = 10): 1 to 10, one per statement/decision.
    • Edges (E = 13): 1-2, 2-3, 2-10, 3-4, 3-5, 4-5, 5-6, 5-7, 6-7, 7-8, 7-9, 8-9, 9-2.
    • Predicate nodes (4): node 2 (loop), nodes 3, 5, 7 (branches).
    1 -> 2 -> 3 -> 4 -> 5 -> 6 -> 7 -> 8 -> 9 -> (back to 2)
         |    \_____/    \_____/    \_____/
         |   (3 skips 4)(5 skips 6)(7 skips 8)
         +-> 10 (loop exit)
    

    Cyclomatic complexity (three equivalent methods)

    1. V(G) = E - N + 2 = 13 - 10 + 2 = 5
    2. V(G) = P + 1 (P = predicate nodes) = 4 + 1 = 5
    3. V(G) = number of regions = 5 (4 bounded regions + 1 outer region)

    Independent paths (V(G) = 5)

    Path Route Meaning
    P1 1-2-10 Loop never entered
    P2 1-2-3-5-7-9-2-10 All branches false
    P3 1-2-3-4-5-7-9-2-10 Branch 1 true
    P4 1-2-3-5-6-7-9-2-10 Branch 2 true
    P5 1-2-3-5-7-8-9-2-10 Branch 3 true

    Each path adds at least one new edge not used by earlier paths, so they are linearly independent.

    Relation to the minimum number of independent paths

    V(G) equals the number of linearly independent paths in the graph. It is therefore the minimum number of test cases needed to execute every statement and every branch at least once (basis path testing). Here at least 5 test cases are required.

    V(G) Risk
    1 to 10 Simple, low risk
    11 to 20 Moderate
    21 to 50 High
    over 50 Untestable

    A complexity of 5 means a simple, easily testable module.

  19. Q5b. A project has 30 external inputs, 60 external outputs, 23 external inquiries, 8 files and 2 external interfaces. The corresponding complexity weights are 4, 5, 4, 10 and 7. Four of the fourteen value-adjustment factors have value 0, four have value 3 and the remaining six have value 4. Calculate the Function Point value.20267m

    Module 3: Software Design & Metrics

    A project has 30 external inputs, 60 external outputs, 23 external inquiries, 8 files and 2 external interfaces. The corresponding complexity weights are 4, 5, 4, 10 and 7. Four of the fourteen value-adjustment factors have value 0, four have value 3 and the remaining six have value 4. Calculate the Function Point value.

    View this question on its own page →
    Worked Solution

    Function Point Calculation

    Formula: FP = UFP x VAF

    • UFP (Unadjusted Function Points) = sum of (count x weight) for the five components
    • VAF (Value Adjustment Factor) = 0.65 + 0.01 x (sum of the 14 factor ratings)

    Step 1: Unadjusted Function Points

    Component Count Weight Count x Weight
    External Inputs (EI) 30 4 120
    External Outputs (EO) 60 5 300
    External Inquiries (EQ) 23 4 92
    Internal Logical Files (ILF) 8 10 80
    External Interface Files (EIF) 2 7 14
    UFP 606

    Step 2: Value Adjustment Factor

    The 14 factors (rated 0 to 5):

    • 4 factors with value 0: 4 x 0 = 0
    • 4 factors with value 3: 4 x 3 = 12
    • 6 factors with value 4: 6 x 4 = 24

    Sum of ratings (ΣFi) = 0 + 12 + 24 = 36

    VAF = 0.65 + 0.01 x 36 = 0.65 + 0.36 = 1.01

    Step 3: Function Points

    FP = UFP x VAF = 606 x 1.01 = 612.06

    Answer

    Function Point value = 612.06 (about 612 FP)

    Since VAF is slightly above 1, the system is a little more complex than average, so the adjusted size is a little higher than the unadjusted count.

  20. Q6a. Compare black-box and white-box testing with respect to information used for test-case design, typical techniques and defect types detected.20267m

    Module 4: Software Testing

    Compare black-box and white-box testing with respect to information used for test-case design, typical techniques and defect types detected.

    View this question on its own page →
    Worked Solution

    Black-Box vs White-Box Testing

    Black-box testing tests the software without looking at the code, using only the specification (inputs and expected outputs).
    White-box testing tests the internal structure and logic of the code.

    Comparison

    Basis Black-box testing White-box testing
    Information used for test-case design Requirements/specification, input and output domains Source code, control-flow and data-flow structure
    Knowledge of code needed No Yes
    Typical techniques Equivalence class partitioning, boundary value analysis, decision table testing, cause-effect graphing, state-transition testing Statement coverage, branch/decision coverage, condition coverage, path testing (basis paths), data-flow testing, mutation testing
    Defect types detected Missing or incorrect functions, interface errors, wrong output, input/output (boundary) errors, incorrect specification handling Logical errors, unreachable or dead code, wrong conditions, loop errors, incorrect data usage, uncovered paths
    Performed by Testers / independent test team Developers
    Test level Mostly system and acceptance Mostly unit and integration
    Limitations Cannot find hidden code paths or dead code Cannot find missing functionality

    Conclusion

    The two are complementary. Black-box testing checks that the software does what the customer asked for; white-box testing checks that the code is built correctly. A good test strategy uses both (grey-box testing combines them).

  21. Q6b. A program accepts marks from 0 to 100. Construct test cases using Boundary Value Analysis and Equivalence Class Testing and compare the resulting test sets.20267m

    Module 4: Software Testing

    A program accepts marks from 0 to 100. Construct test cases using Boundary Value Analysis and Equivalence Class Testing and compare the resulting test sets.

    View this question on its own page →
    Worked Solution

    Test Cases for Marks (0 to 100): BVA and Equivalence Class Testing

    Valid range: 0 <= marks <= 100 (integers). Anything else must be rejected with an error message.

    1. Boundary Value Analysis (BVA)

    Test at and around each boundary (min-1, min, min+1, nominal, max-1, max, max+1):

    TC Input Expected output
    B1 -1 Invalid (just below minimum)
    B2 0 Valid (minimum)
    B3 1 Valid (just above minimum)
    B4 50 Valid (nominal)
    B5 99 Valid (just below maximum)
    B6 100 Valid (maximum)
    B7 101 Invalid (just above maximum)

    Total = 7 test cases (robust BVA). Standard BVA without the two invalid values has 5.

    2. Equivalence Class Testing (ECT)

    Divide the input domain into classes whose members behave alike; test one value per class.

    Class Range Type Representative input Expected output
    EC1 marks < 0 Invalid -20 Error
    EC2 0 to 100 Valid 55 Accepted
    EC3 marks > 100 Invalid 150 Error

    Non-integer or non-numeric input (e.g. "abc") can be added as a further invalid class.

    Total = 3 test cases (4 with the non-numeric class).

    3. Comparison of the test sets

    Basis BVA Equivalence class testing
    Number of tests 7 3
    Focus Edges of ranges, where off-by-one errors occur (e.g. < written instead of <=) Whole classes of input, one representative each
    Defect finding Strong for boundary errors Strong for general class errors, weak at boundaries
    Redundancy Higher Minimal

    Example: if the code wrongly checks marks < 100, ECT value 55 passes but BVA input 100 exposes the bug.

    Conclusion

    ECT reduces the number of tests; BVA finds boundary defects. Using them together (for example 3 + the boundary values) gives better coverage with a small test set.

  22. Budget App•POCKETLY

    Pocketly on Android

    Log daily food, travel, and hostel expenses instantly. Set monthly spending limits and see where your money goes without complex spreadsheets.

    Install Pocketly
  23. Q7a. Analyse the need for software maintenance and categorize suitable maintenance activities for changes caused by defects, operating-environment changes and new user requirements.20267m

    Module 5: Software Maintenance

    Analyse the need for software maintenance and categorize suitable maintenance activities for changes caused by defects, operating-environment changes and new user requirements.

    View this question on its own page →
    Worked Solution

    Need for Software Maintenance and Categories of Maintenance

    Software maintenance is the modification of software after delivery to correct faults, improve performance or adapt it to a changed environment.

    Need for maintenance

    1. Defects remain after delivery: testing cannot find every fault.
    2. Environment changes: new operating systems, hardware, databases, laws or tax rules.
    3. New user requirements: users ask for new features or improvements once they use the system.
    4. Prevent decay: repeated changes degrade the structure; software must be restructured to stay maintainable.
    5. Long life of software: maintenance is typically the largest part (often 60% or more) of total life-cycle cost.

    Types of maintenance

    Type Purpose Trigger
    Corrective Fix errors/bugs found after delivery Defects
    Adaptive Modify software to work in a changed environment OS, hardware, platform, regulation changes
    Perfective Add or improve features and performance New or changed user requirements
    Preventive Improve structure/readability to avoid future problems Reduce future maintenance cost

    Mapping the given changes

    Cause of change Maintenance category Example
    Defects Corrective Fixing a wrong tax calculation
    Operating-environment changes Adaptive Porting the app to a new OS version or database
    New user requirements Perfective Adding a report or a new payment option

    Preventive maintenance (code cleanup, refactoring, updating documentation) applies when there is no immediate trigger but the code is becoming hard to change.

    Typical effort split

    Perfective is usually the largest share (about 50%), then adaptive (about 25%), corrective (about 20%) and preventive (about 5%).

  24. Q7b. A healthcare company plans an application through which patients can register, consult doctors online, upload medical reports, receive prescriptions and make payments. Requirements are expected to evolve after pilot deployment. Analyse the requirement and formulate an appropriate SDLC strategy, major functional and nonfunctional requirements, one suitable prototyping activity and two risks that should influence process selection.20267m

    Module 1: Introduction & SDLC

    A healthcare company plans an application through which patients can register, consult doctors online, upload medical reports, receive prescriptions and make payments. Requirements are expected to evolve after pilot deployment. Analyse the requirement and formulate an appropriate SDLC strategy, major functional and nonfunctional requirements, one suitable prototyping activity and two risks that should influence process selection.

    View this question on its own page →
    Worked Solution

    Healthcare Application: Requirement Analysis and SDLC Strategy

    1. Requirement analysis

    Stakeholders: patients, doctors, administrators, pharmacy/lab staff, payment provider.
    Key points: health data is sensitive, so privacy and security are critical; requirements are expected to evolve after the pilot, so the process must absorb change.

    2. Major functional requirements

    • FR1 Patient registration and login
    • FR2 Doctor search and appointment booking
    • FR3 Online consultation (video/chat)
    • FR4 Upload and view medical reports
    • FR5 Doctor issues e-prescription; patient views/downloads it
    • FR6 Online payment and receipts
    • FR7 Notifications and reminders
    • FR8 Admin: manage users, doctors and reports

    3. Major non-functional requirements

    Quality Requirement
    Security & privacy Encrypted data, role-based access, consent, audit log, compliance with health-data laws
    Availability High uptime, especially for consultations
    Performance Fast page loads, smooth video, large report uploads
    Usability Simple UI for non-technical patients and elderly users
    Reliability/Integrity Prescriptions and reports must never be lost or altered
    Scalability Handle growth in patients and doctors
    Interoperability Work with payment gateways and hospital systems

    4. Appropriate SDLC strategy

    Iterative-incremental with prototyping, run in an Agile/Spiral style.

    • Requirements are unclear and will change after the pilot, so a one-pass Waterfall is unsuitable.
    • Build and release in increments: registration and booking first, then consultation, then reports and prescriptions, then payments.
    • Use the pilot deployment as a feedback cycle; update the backlog before the next increment.
    • Add a risk review in every cycle (Spiral element) because of the sensitive data.

    5. One prototyping activity

    Build a throw-away UI prototype of the appointment booking and online consultation flow (clickable wireframes). Show it to a few patients and doctors, collect feedback on screens, navigation and steps, then refine the requirements before coding.

    6. Two risks that influence process selection

    Risk Effect on process choice
    Requirement volatility after the pilot Needs an iterative/incremental model with change handling
    Data privacy / regulatory compliance and security breaches Needs early and repeated security review (risk analysis every cycle), traceable documentation

    Other possible risks: payment-gateway failures, video-service downtime, low user adoption.

    Conclusion

    An iterative, incremental, prototype-driven process with risk analysis (Agile/Spiral hybrid) fits best: it manages changing requirements while keeping security and privacy under control.

  25. Q8a. Compare reverse engineering and software reengineering with respect to objectives, activities, outputs and their role in modernizing legacy systems.20267m

    Module 5: Software Maintenance

    Compare reverse engineering and software reengineering with respect to objectives, activities, outputs and their role in modernizing legacy systems.

    View this question on its own page →
    Worked Solution

    Reverse Engineering vs Software Re-engineering

    Reverse engineering = analysing an existing system (usually just the code or binary) to recover its design, specification and understanding. It does not change the software.
    Re-engineering = restructuring or rewriting an existing system to improve quality or move it to a new platform, while keeping its functionality. It includes reverse engineering as a first step.

    Comparison

    Basis Reverse engineering Software re-engineering
    Objective Understand the system and recover design/requirements when documentation is missing Improve maintainability, performance or platform of a legacy system
    Changes the software? No (analysis only) Yes (restructure, convert, rewrite)
    Main activities Code reading and analysis, extracting data and control flow, building structure charts, UML/ER diagrams, documentation Reverse engineering, restructuring/refactoring code and data, translating to a new language/platform, forward engineering, retesting
    Outputs Design documents, models, call graphs, recovered requirements A restructured/migrated system that behaves the same way, plus updated documentation
    Direction Backward (code to design) Backward then forward (code to design to new code)
    Effort and cost Lower Higher, but lower than a full rewrite

    Re-engineering process

    Inventory analysis, document restructuring, reverse engineering, code restructuring, data restructuring, forward engineering, testing.

    Role in modernizing legacy systems

    Legacy systems are old, poorly documented and costly to maintain.

    1. Reverse engineering first recovers lost knowledge of how the system works.
    2. Re-engineering then restructures it or moves it to modern technology (new language, database, cloud) without rewriting from scratch.
    3. Result: lower maintenance cost, better quality, longer system life, and less risk than building a new system.

    Reverse engineering is the analysis stage; re-engineering is the full modernization process that uses it.

  26. Q8b. A development team maintains five released versions of the same product. Design a configuration-management structure showing configuration items, version identification, change control and release management.20267m

    Module 5: Software Maintenance

    A development team maintains five released versions of the same product. Design a configuration-management structure showing configuration items, version identification, change control and release management.

    View this question on its own page →
    Worked Solution

    Configuration-Management Structure for a Product with Five Released Versions

    Software Configuration Management (SCM) keeps every released version identifiable, reproducible and controlled while several versions are maintained at the same time.

    1. Configuration items (CIs)

    Category Items
    Requirements/design SRS, design documents, architecture diagrams
    Source Source code, libraries, configuration files
    Build/deploy Build scripts, installers, environment settings
    Test Test plans, test cases, test data, results
    Data Database schema and migration scripts
    User User manual, release notes

    2. Version identification

    Use semantic versioning: MAJOR.MINOR.PATCH (e.g. 3.2.1)

    • MAJOR: incompatible or large changes
    • MINOR: new backward-compatible features
    • PATCH: bug fixes only

    Baselines are frozen, approved sets of CIs (e.g. v1.0, v2.0). Each CI and each build is tagged with its version.

    main (latest development)
     |--- release/1.x  --> 1.0, 1.0.1, 1.1 ... (maintenance branch)
     |--- release/2.x  --> 2.0, 2.0.1 ...
     |--- release/3.x  --> 3.0, 3.1 ...
     |--- release/4.x  --> 4.0, 4.2 ...
     |--- release/5.x  --> 5.0, 5.1 ...   (current)
    

    Each released version has its own maintenance branch; a fix is applied to the affected branches and merged back to main.

    3. Change control process

    1. Change request raised (bug, enhancement, environment change)
    2. Impact analysis: which CIs and versions are affected
    3. Change Control Board (CCB) reviews and approves or rejects
    4. Implementation on a branch
    5. Verification: review and regression testing
    6. Merge and baseline update, change log recorded
    7. Status reporting and audit

    4. Release management

    Activity Purpose
    Release planning Decide which fixes/features go into which version
    Build and package Reproducible build from tagged CIs
    Release notes List changes, known issues, upgrade steps
    Deployment and rollback plan Safe installation with a way back
    Support policy Define how long each version is maintained
    Audit Check that the released build matches the approved baseline

    Tools

    Git/SVN for version control, Jenkins/CI for builds, Jira for change requests.

    Benefit

    Any of the five versions can be rebuilt exactly, bugs can be traced to the version they affect, and changes are controlled and recorded.

  27. Q9a. Write short notes on any two of the following: Functional and Non-functional Requirements20267m

    Module 2: Requirements & SRS

    Write short notes on any two of the following:

    Functional and Non-functional Requirements

    View this question on its own page →
    Worked Solution

    Functional and Non-functional Requirements

    Functional requirements (FR)

    Describe what the system must do: its functions, features, inputs, processing and outputs.

    • Example (online shopping): The system shall allow a user to add items to a cart, place an order and receive an order confirmation.
    • Written as "The system shall..."; tested by black-box functional tests.

    Non-functional requirements (NFR)

    Describe how well the system must work: quality attributes and constraints.

    • Categories: performance, security, reliability, availability, usability, portability, maintainability, scalability, plus legal and standards constraints.
    • Example: The system shall respond to a search within 2 seconds for 500 simultaneous users.

    Comparison

    Basis Functional Non-functional
    Describes What the system does How the system performs (quality)
    Focus Features and behavior Quality attributes and constraints
    Source User/business needs Standards, constraints, quality goals
    Verification Functional testing Performance, security, usability testing
    If missing System cannot do its job System is unusable, slow or unsafe
    Example Login, generate invoice Login in under 2 s, 99.9% uptime

    Importance

    Both must be recorded in the SRS. A system that meets all functional requirements but fails its NFRs (slow, insecure) is still a failure.

  28. Q9b. Write short notes on any two of the following: Top-down and bottom-up approach20267m

    Module 3: Software Design & Metrics

    Write short notes on any two of the following:

    Top-down and bottom-up approach

    View this question on its own page →
    Worked Solution

    Top-Down and Bottom-Up Approach

    Top-down design

    Start with the overall system and repeatedly break it into smaller sub-systems/modules until each module is simple enough to code (stepwise refinement).

    • Begins with the main module and works down; lower modules are first replaced by stubs.
    • Example: Banking system, then Accounts / Loans / Transactions, then Deposit, Withdraw, Transfer.
    • Advantages: clear overall structure, early detection of design and interface errors, easy to manage.
    • Disadvantages: low-level details come late; reuse of existing components is limited.

    Bottom-up design

    Start by designing and building the lowest-level, basic modules, then combine them into larger modules until the whole system is built.

    • Uses drivers to test lower modules first.
    • Example: Build and test Deposit, Withdraw and Transfer first, then combine them into Transactions, then the Banking system.
    • Advantages: encourages reuse of existing modules, low-level modules are tested thoroughly, suits projects built on existing libraries.
    • Disadvantages: overall structure and interface problems appear late; system-level design is unclear at the start.

    Comparison

    Basis Top-down Bottom-up
    Starts from Whole system / main module Lowest-level modules
    Direction Decomposition (divide) Composition (combine)
    Testing aid Stubs Drivers
    Strength Clear structure, early design validation Reuse, early detail testing
    Weakness Late low-level detail Late integration problems

    In practice a combination of both is used.

  29. Q9c. Write short notes on any two of the following: Alpha & beta testing20267m

    Module 4: Software Testing

    Write short notes on any two of the following:

    Alpha & beta testing

    View this question on its own page →
    Worked Solution

    Alpha and Beta Testing

    Both are forms of acceptance testing done before a product's final release.

    Alpha testing

    • Performed in-house at the developer's site, in a controlled environment, by the development/QA team or internal users.
    • Done before beta testing, when the product is nearly complete.
    • Uses both white-box and black-box techniques; defects are fixed immediately.
    • Goal: find major bugs and crashes early.

    Beta testing

    • Performed at the customer's site, in the real environment, by a limited group of real end users.
    • Done after alpha testing, just before public release.
    • Mainly black-box; the developer is not present.
    • Users report bugs, usability problems and compatibility issues.
    • Goal: validate the product under real conditions and gather feedback.
    • Example: pre-release app versions offered to a small group of users.

    Comparison

    Basis Alpha testing Beta testing
    Performed by Developers / internal testers Real end users / customers
    Location Developer's site User's site (real environment)
    Environment Controlled Uncontrolled, real world
    Timing Before beta After alpha, before release
    Technique White and black box Black box
    Bug fixing Immediate Collected, fixed in later versions
    Purpose Find major defects early Check real-world use, gather feedback

    Significance

    Together they reduce the chance that serious defects reach the public, improve quality and usability, and increase customer confidence.

  30. Q9d. Write short notes on any two of the following: SRS standards20267m

    Module 2: Requirements & SRS

    Write short notes on any two of the following:

    SRS standards

    View this question on its own page →
    Worked Solution

    SRS Standards (IEEE)

    An SRS (Software Requirements Specification) is the document that states what the software must do and acts as an agreement between client and developer. Standards give a common structure so every SRS is complete and consistent.

    Main standards

    • IEEE 830-1998: Recommended Practice for Software Requirements Specifications (the classic SRS format used in syllabi).
    • ISO/IEC/IEEE 29148:2018: the current standard that replaced IEEE 830 and covers requirements engineering processes and documents.

    IEEE 830 structure

    1. Introduction
      • 1.1 Purpose, 1.2 Scope, 1.3 Definitions, acronyms, abbreviations, 1.4 References, 1.5 Overview
    2. Overall description
      • 2.1 Product perspective, 2.2 Product functions, 2.3 User characteristics, 2.4 Constraints, 2.5 Assumptions and dependencies
    3. Specific requirements
      • External interfaces (user, hardware, software, communication)
      • Functional requirements
      • Performance requirements
      • Design constraints
      • Software system attributes (reliability, availability, security, maintainability, portability)
      • Other requirements
    4. Appendices and index

    Characteristics of a good SRS (IEEE 830)

    Correct, unambiguous, complete, consistent, ranked for importance/stability, verifiable, modifiable, traceable.

    Benefits of following a standard

    • Common understanding between client, analysts and developers
    • Fewer missing or conflicting requirements
    • Easier review, testing and maintenance
    • Basis for estimating cost and schedule
Free AppAndroid App

Coursify Android App

Generate AI courses, take quick quizzes between classes, and master complex engineering concepts on the go.